cv {PRA} | R Documentation |
Cost Variance (CV).
Description
Cost Variance (CV).
Usage
cv(ev, ac)
Arguments
ev |
Earned Value. |
ac |
Actual Cost. |
Value
The function returns the Cost Variance (CV) of work completed.
Examples
# Set the BAC and actual % complete for an example project.
bac <- 100000
actual_per_complete <- 0.35
# Calcualte the EV
ev <- ev(bac, actual_per_complete)
# Set the actual costs and current time period and calculate the AC.
actual_costs <- c(9000, 18000, 36000, 70000, 100000)
time_period <- 3
ac <- ac(actual_costs, time_period)
# Calculate the CV and print the results.
cv <- cv(ev, ac)
cat("Cost Variance (CV):", cv, "\n")